USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

South Avenue Safety Project

PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-2/d2-projects/d2-south-avenue-safe…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/27/2022

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The California Department of Transportation, using state and federal funding, proposes to reconfigure the existing intersection of SR 99 and South Avenue in Tehama County by replacing the existing minor leg stop-controlled only intersection with a roundabout; the limits of work on State Route 99 are from post mile 4.20 to 4.80.  The purpose of the project is to reduce the frequency and severity of collisions by at least 50 percent.  The project is needed because there were 17 collisions along this section of roadway between July 1, 2010 and June 30, 2015.  The roundabout would consist of a center island with mountable curb, textured median paving, and interior curb. The roundabout would have an inscribed diameter that is 165 feet.  This diameter, along with a circling single lane and truck apron width of up to 45 feet, would accommodate all vehicle sizes from bicycles to Surface Transportation Assistance Act (STAA) trucks.  Traffic speed in the roundabout would be 25 miles per hour (MPH).

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete