South Madera 6-Lane

PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-6/district-6-projects/06-0h220

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/22/2021

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Other Agencies with Actions or Authorizations:

California

California

Description:

The California Department of Transportation (Caltrans) proposes the South Madera 6 lane project. The purpose of this project is to reduce congestion by increasing capacity, improving connectivity of the highway system, and preserving acceptable facility operation of State Route 99 in Madera County. This segment of freeway currently operates at level of service “D” and will operate at level of service “F” by 2020 without improvements. The project would widen the existing 4-lane facility to a 6-lane freeway between post miles R1.7 and R7.5. There are 3 build alternatives and the no-build alternative under consideration. All build alternatives would include the construction of a new California Highway Patrol weigh station on the southbound side of the freeway.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete