Southwest Light Rail Transit
PROJECT WEBSITE: Metropolitan Council's Southwest LRT Web page
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/15/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Other Agencies with Actions or Authorizations:
Minnesota
Department of Defense
Description:
The Metropolitan Council is the project sponsor for the Southwest Light Rail Transit (LRT) Project (METRO Green Line Extension). The project will operate provide new light rail service from downtown Minneapolis through the communities of St. Louis Park, Hopkins, Minnetonka, and Eden Prairie, passing in close proximity to Edina. The proposed project would add over 14 miles of new track as well as 15 new stations, several of which will have park-and-ride lots. It would be part of an integrated system of transitways, including connections to the METRO Blue Line, the Northstar Commuter Rail line, bus routes, and proposed future transitways. The LRT line would link several major activity centers, including Target Field on the corridor's eastern end and the Eden Prairie Center Mall on the corridor's western end. At Target Field Station in Minneapolis, Green Line Extension trains will continue along the METRO Green Line, providing one-seat rides to the University of Minnesota, State Capitol area, and downtown St. Paul.
*This project was identified Regionally or Nationally Significant in the original Permitting Dashboard
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|