SR 11 Roadway Project
PROJECT WEBSITE: https://www.sr11extension.com/about
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/29/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
States
Description:
The SR 11 Roadway Project includes connecting SR 11 and SR 135 in southern Harrison County, Indiana with a roadway the meets current design standards, including a new bridge crossing of Buck Creek. The need for the project is to improve the safety of the roadway network in southern Harrison County by reducing traffic on local roadways which do not meet current design standards and currently have high RoadHAT indices for both crash frequencies and crash costs.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|