SR 124 FROM US 78 TO SR 864/RONALD REAGAN PARKWAY

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/28/2029

3 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

SR 124/Scenic Highway would be widened to six travel lanes (three in each direction), with approximately a 5 to 27-foot variable raised median and a 5-foot sidewalk or a 10-foot shared-use path (SUP). Approximately 140-250 feet of right-of-way width will be needed to accommodate the minimum width needed for the Preferred Alternative. Both temporary and permanent easements are anticipated; permanent easements would include those needed for utility relocation. The new third northbound travel lane would begin approximately 250 feet north of the US 78 intersection and tie into the existing right-turn lane at Pharrs Road (project ends 200 feet south of Pharrs Road). The intersection at Ronald Reagan Parkway and Pinehurst Road would be upgraded with displaced dual left-turn lanes for the northbound SR 124/Scenic Highway movement onto westbound Ronald Reagan Parkway, forming a single-leg Continuous Flow Intersection (CFI) in the southwest quadrant. The southbound SR 124/Scenic Highway left-turn lane onto Pinehurst Road would be extended, and a new right-turn lane from northbound SR 124/Scenic Highway onto Pinehurst Road would be added. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete