SR 395 Sonora Junction Shoulders
PROJECT WEBSITE: Sonora Junction Shoulder Widening Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/01/2023
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:
California
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The California Department of Transportation (Caltrans), proposes the Sonora Junction Shoulders project on US 395, the purpose of this project is to enhance highway safety and make the road accessible to multiple modes of transportation. The project is needed due to the existing 2ft shoulders not meeting current design standards. The proposed project has 3 "build" and one "no-build" alternative. The build alternatives range from full 8ft wide shoulders throughout the project limits, 4ft shoulders throughout, and a hybrid (variable 8ft and 4ft) throughout.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|