SR91: Westbound Improvement Project

PROJECT WEBSITE: WB SR-91 Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/17/2019

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Other Agencies with Actions or Authorizations:

California

California

Description:

The California Department of Transportation (Caltrans) District 7 and the Los Angeles County Metropolitan Transportation Authority (Metro), in collaboration with the Gateway Cities Council of Governments (GCCOG) and the Cities of Cerritos and Artesia, propose to widen and improve approximately 4 miles (mi) of freeway along westbound State Route 91 (SR-91) between approximately Shoemaker Avenue and the Interstate 605 (I-605) interchange, and at the I-605 northbound exit to Alondra Boulevard. The Study Area includes westbound SR-91 (Post Miles [PM] 16.9–19.8) and northbound I-605 (PM 5.0–5.8) and traverses the cities of Cerritos and Artesia.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete