St. Louis Lambert International Airport for Boeing Site Development, Environmental Assessment
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/15/2023
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Description:
An Environmental Assessment (EA) is being prepared for the proposed Boeing Site Development subject to the National Environmental Policy Act (NEPA). The Federal Aviation Administration (FAA) is the lead federal agency for the NEPA document. St. Louis Lambert International Airport (STL) is proposing to lease two locations, referred to as Northern Tract and Brownleigh, to the Boeing Company (Boeing) for the construction of an aircraft assembly building and an associated flight ramp. On the Northern Tract site, the project includes demolition of extant buildings and construction of new flight ramp structures, hangar, fuel calibration, radar cross section, hush house, and open-air shelters. At the Brownleigh site, construction of a 880,000 SF manufacturing facility.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|