State Route 37 Flood Reduction Project

PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-4/d4-popular-links/d4-environmenta…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/01/2026

1 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Description:

State Route 37 Flood Reduction Project - The Project proposes a causeway that would be 35 feet in elevation and consist of four 12-foot-wide lanes, a 22-foot-wide median with a 2-foot-wide median barrier, two 10-foot-wide inside shoulders, two 12-foot-wide outside shoulders, two 2-foot-wide outside barriers, and a 14-foot-wide bicycle or pedestrian path with a 2-foot-wide barrier, for a total roadway width of 114 feet. There would be no change to the longterm vehicular capacity on SR 37. To maintain regional connectivity, the Project Summary State Route 37 Flood Reduction Project viii Environmental Impact Report/Environmental Assessment would be phased with the most flood-prone component, the Novato Creek Bridge and connecting structures, being built in Phase 1. Phase 2 would raise the rest of SR 37 within the Project area to reduce flooding and improve resiliency.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete