State Route 9: San Lorenzo River and Kings Creek Bridge Replacement
PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-5/district-5-current-projects/05-1…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/01/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of Commerce, National Oceanic and Atmospheric Administration
California
Department of the Interior, Fish and Wildlife Service
Description:
The California Department of Transportation (Caltrans) proposes to replace two ageing bridges along State Route (SR) 9 in Santa Cruz County, within the boundary of the Boulder Creek Census Designated Place: the 80-year-old San Lorenzo River Bridge (No. 36-0052) and 90-year-old Kings Creek Bridge (No. 36-0054). The San Lorenzo River Bridge is located about 0.5 miles north of the town core of Boulder Creek (Post Mile [PM] 13.6), and the Kings Creek Bridge is located in the Redwood Grove neighborhood (PM 15.5). State Route 9 near the project is a rural, 2-lane undivided conventional highway that runs through the Santa Cruz Mountains, along the steep banks of the San Lorenzo River.
Both existing bridges are older than the typical 75-year service life of a bridge and have been found to be structurally deficient. The San Lorenzo River Bridge exhibits deck and soffit distress, cracking, and poor paint condition, while the foundation of the Kings Creek Bridge is vulnerable to scour related issues. Both bridges also have non-standard bridge railings, non-standard sidewalks, and lack shoulders.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|