USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

State Route (SR) 11/Murphy Highway from Blue Ridge Street to SR 325/Ivylog Road

PROJECT WEBSITE: https://sr-11-widening-union-gdot.hub.arcgis.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/20/2026

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

122200-: This project proposes to widen and reconstruct SR 11/US 19 & 129/Murphy Highway from just south of the intersection with SR 515/US 76 north to Gumlog Road including the construction of roundabouts at Pat Haralson Memorial Drive, Pat Colwell Road, and Gumlog Rd. The project will construct four lanes from SR 515 to Pat Colwell Road and three lanes from Pat Colwell Road to Gumlog Road. The project length is 5.30 miles.
0018219: This project proposes to construct at roundabout at the intersection of Blue Ridge Street and Murphy Hwy in Blairsville to replace the 4-way stop sign controlled intersection. The project length is 0.50 miles.
0018220: This project proposes to widen and reconstruct SR 11/ US 19 & 129/Murphy Hwy from two to three lanes from Gumlog Road to SR 325/Ivylog Road. The project length is 3.40 miles. The project will tie into the ends of the existing bridge over Ivy Log Creek and not replace or improve this bridge.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete