State Route (SR) 241 to SR 91 Direct Connector
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/12/2020
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:

California
Department of the Interior, Fish and Wildlife Service
Description:
The Proposed Project, located at the junction of State Route 241 (SR-241) and State Route 91 (SR-91) in the cities of Anaheim, Yorba Linda, and Corona, and the counties of Orange and Riverside, would provide improved access between SR-241and SR-91, and is proposed to be a tolled facility. The proposed median-to-median connector project encompasses 12-ORA-241 (Post Mile [PM] 36.1/39.1), 12-ORA-91 (PM 14.7/18.9), and 08-RIV-91 (PM 0.0/1.5) for a total length of approximately 8.7 miles (mi).
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|