Sun River Bridge Replacement
PROJECT WEBSITE: https://highways.dot.gov/federal-lands/projects/mt/flap-bor-2980-1
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/29/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
States
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The Federal Highway Administration (FHWA) is developing a project to replace the Sun River Bridge in cooperation with the U.S. Bureau of Reclamation (USBR), U.S. Bureau of Land Management (USBLM), U.S. Forest Service (USFS), and Greenfields Irrigation District (GID). FHWA will serve as the lead agency in preparing the Sun River Bridge Replacement Environmental Assessment (EA).
FHWA, in cooperation with partner agencies, proposes to replace the existing single-lane structurally deficient bridge with a new bridge meeting current design and safety standards. The project would provide service continuity for a variety of federal, state, and local agencies, as well as residents, outfitters, law enforcement, and emergency responders. The existing Sun River Bridge is structurally deficient and functionally obsolete. Its poor condition and outdated design pose safety hazards and limitations to users. A new bridge is needed to provide a crossing over the Sun River that safely and reliably accommodates all users.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|