USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Toksook Bay Airport and Access Road Rehabilitation, Environmental Assessment

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/31/2018

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation

SECTOR
Aviation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Description:

The proposed project would rehabilitate and improve the Toksook Bay Airport and access road to extend the service life of the facilities. The proposed work would include the following:

  • Rehabilitate the existing runway (RW) 16-34
  • Rehabilitate the existing taxiway (TW)
  • Extend and/or widen the Runway Safety Area (RSA) and Taxiway Safety Area (TSA) to meet B-II safety area standards
  • Extend the runway protection zones (RPZs)
  • Rehabilitate and widen the existing airport access road
  • Construct a new, heated, single bay snow removal equipment building (SREB), including associated electrical work, fuel lines, and fuel storage
  • Geotechnical investigation drilling (Figure 2)
  • Install new lighting on TW and RW 16-34
  • Improve, replace, or extend culverts
  • Apply dust palliative to apron, RW, TW, and access road

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete