USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Tucson-Phoenix Passenger Rail

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/19/2016

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Railroad Administration

Description:

The Passenger Rail Study between Tucson and Phoenix explores intercity rail connections between the two largest metropolitan areas in Arizona. Arizona will use this Study to analyze and develop future intercity rail options.  The proposed passenger rail line will be designed as a blended service: An express service would have few stops between Tucson and Phoenix, and a local service would stop at several communities along the way.  Phoenix is the only metropolitan area with over a million people in the United States that is not served by passenger rail.

Currently, there is no construction schedule and no funding identified for a project to build an intercity rail system between Phoenix and Tucson. It will be up to the public and policymakers to decide if such an effort is feasible and how to generate the funding to pay for implementation of the Study.

Draft Tier 1 EIS

Notice of Intent was published in the Federal Register on October 6, 2011 to initiate the environmental impact statement process for the Study.

The Arizona Department of Transportation (ADOT) identified a need for an alternative transportation mode to help meet existing and future travel demand in the Pima, Pinal, and Maricopa tri-county area. By 2035, the travel time between Tucson and Phoenix via Interstate 10 (I-10) is projected to take 26 percent longer than the travel time in 2010 and, by 2050, 59 percent longer, even if the highway is widened to 10 lanes. The Arizona Passenger Rail Corridor Study (APRCS), led by the Federal Railroad Administration (FRA), builds on statewide and regional planning efforts and initiatives to investigate alternative approaches to implementing passenger rail service between Tucson and Phoenix, Arizona’s two largest cities.

ADOT’s study team developed a range of corridor alternatives with the goals of serving key population and activity centers, maximizing potential ridership, minimizing environmental impacts, and being cost effective. An iterative planning and outreach process identified potential routes; these were documented in an Alternatives Analysis (AA) report. Each has undergone multidisciplinary consideration, leading to a set of corridor alternatives.

Two corridor alternatives, in addition to a No Build Alternative, are examined in the Draft Tier 1 Environmental Impact Statement (EIS), through a process prescribed by the Council on Environmental Quality in compliance with the National Environmental Policy Act (NEPA).

The Draft Tier 1 EIS for the APRCS analyzes the natural, built, and social environment that may be affected by alternative actions being considered and identifies the potential environmental effects of each so they can be compared to one another and to the effects of taking no action (the No Build Alternative). The information, analysis, and comparison of effects, as well as input received from the public, are intended to aid government agencies in making decisions about public expenditures and infrastructure investment.

 

The Final EIS and Record of Decision was executed by the FRA on December 19, 2016. The document is in the January 6, 2017 Federal Register.


In addition, pertinent information can be found at the project's FRA webpage, https://www.fra.dot.gov/Page/P0720.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete