(TX) Borderland Expressway
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/31/2023
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
Borderland Expressway Project (formerly known as Northeast Parkway Project), El Paso District
Project limits: On SL 375 East of Railroad Drive Overpass to FM 3255 Martin Luther King, Jr. Blvd. @ TX-NM
CSJ Numbers: 0924-06-136, 0924-06-320
The Texas Department of Transportation (TxDOT) proposes to construct an alternative route to Interstate 10 (I-10) through El Paso that meets the future transportation needs of the El Paso Metropolitan Area. The ultimate design of the proposed Borderland Expressway Project (formerly known as the Northeast Parkway Project) is a 10.8-mile long, four-lane, limited access, new location facility within a 350-foot right-of-way (ROW) and includes five interchanges.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|