(TX) Downtown 10 (El Paso Executive Center Blvd to SL 478)

PROJECT WEBSITE: https://www.txdot.gov/reimaginei10/downtown10.html

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/03/2024

0 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

Proposed improvements may include widening and reconstruction of the mainlanes and reconstruction of cross streets. In addition, improvements may include the 
construction of retaining walls, bridges, and ramps, as well as the development of continuous frontage roads. Multimodal connections for pedestrians, cyclists, and 
transit users are also proposed.

Additionally, ROW is proposed for the project. The ROW footprint will not be set until preferred alternative(s) are chosen. Currently, the largest proposed ROW for an alternative is approximately 31.5 acres. The proposed project’s drainage system is under evaluation.
 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete