(TX) FM 70/SH 286 Passing Lanes

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/02/2023

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The proposed project would widen the roadway on SH 286 and FM 70 to construct passing lanes and shoulders. One passing lane section would be constructed in each direction on SH 286. Five passing lane sections would be constructed in each direction on FM 70. Passing lane sections would vary from between 1.7 miles and 3.7 miles in length. In non-passing lane sections, the roadway would be widened to add 10-ft shoulders. In passing lane sections the proposed roadway would include three 12-ft travel lanes with 10-ft shoulders. Ditches would be re-aligned and regraded to accommodate the widening and maintain proper drainage. Culverts would be extended or replaced, where needed, to accommodate the roadway widening.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete