(TX) IH-35 Capital Express South
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/21/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
The Texas Department of Transportation is proposing improvements to I-35 from US 290 West/State Highway (SH) 71 (SH 71) to SH 45 southeast (SE) in Travis County, with a transition area extending to Main Street in Buda, Hays County. The proposed improvements would add two non-tolled managed high-occupancy vehicle (HOV) lanes in each direction, reconstruct intersections and bridges to increase bridge clearances and east/west mobility, and improve bicycle and pedestrian accommodations along I-35 frontage roads and at east/west crossings. The project length is approximately 10-miles (mi). The project would require the acquisition of approximately 13.45 acres of right of way (ROW). There would not be displacements as a result of the proposed project.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|