(TX) SH 42
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/12/2020
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
Texas
Description:
The proposed project would widen the existing facility to a four‐lane divided highway with two 12‐foot
travel lanes in each direction, a 14–16‐foot center left‐turn lane, and shoulders varying in width from six
feet to 10 feet, depending on location, within a variable width right of way of 132–153 feet . The proposed project would also include eight‐foot sidewalks on both sides of the roadway
for a portion of the project length.
The length of the proposed project is approximately 5.9 miles. The proposed improvements would
utilize 87.2 acres of existing right of way. Approximately 90.7 acres of new right
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|