US 101/SR 92 DIRECT CONNECTORS

PROJECT WEBSITE: District 4 Environmental Documents by County

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/26/2027

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Description:

Caltrans, in cooperation with the San Mateo County Transportation Authority and the City/County Association of Governments of San Mateo County, proposes to create a dedicated connection between SR 92 and the US 101 Express Lanes. Currently, there is no existing High Occupancy Vehicle (HOV) direct connector between US 101 Express Lanes and SR 92 that might provide incentives for carpool or bus use. Once completed, the project would provide better connectivity between the US 101 Express Lane and SR 92 to improve operational efficiency and encourage carpooling and the use of shuttles and buses.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete