US 36 Added Travel Lanes

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/13/2020

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Other Agencies with Actions or Authorizations:

No icon

States

No icon

Department of Defense, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Federal Highway Administration (FHWA) and the INDOT Crawfordsville District propose to proceed with an added travel lanes project located on US 36, known locally as Rockville Road, through the Town of Avon in Hendricks and Marion Counties, Indiana. The project limits on US 36 exten east from Shiloh Park Drive to approximately 1,500 feet east of Raceway Road, for a total length of approximately 1.1 miles.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete