US 380 Farmersville

PROJECT WEBSITE: https://www.txdot.gov/projects/hearings-meetings/dallas/2023/us380-farmersville…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/30/2023

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The new location realignment of US 380 will extend for a total of 7.6 miles, from CR 560 to CR 699 (Hunt County Line). The proposed project would also include approximately 4.0 miles of improvements to cross streets in order to create new intersections with the proposed project.  Those cross streets include (parentheses indicate the total estimated length of improvements at that cross street):  Audie Murphy Parkway near the western project limits (1,300 feet or 0.2 mile), CR 607 (1,300 feet or 0.2 mile), SH 78 (4,400 feet or 0.8 mile), CR 609 (500 feet or 0.1 mile), Old Josephine Road (3,300 feet or 0.6 mile), CR 547 (3,800 feet or 0.7 mile), CR 697 (2,100 feet or 0.4 mile), CR 696 (1,500 feet or 0.3 mile), Audie Murphy Parkway near the eastern project limits (1,400 feet or 0.3 mile), and CR 699 (1,900 feet or 0.4 mile).  

To facilitate the transition back to existing US 380/Audie Murphy Parkway, the western limits of construction would extend approximately 2,480 feet or 0.47 mile west of CR 560 and the eastern limits of construction would extend approximately 2,500 feet or 0.5 mile east of CR 699 (Hunt County Line).

The proposed project would require the realignment of US 380 on new location, thus requiring a proposed right-of-way width of approximately 270 feet wide (on the west end) to 542 feet wide (at the KCS RR). Existing US 380 would remain.
 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete