USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

US 51 Stoughton Road North (WIS 30 to I-39/90/94)

PROJECT WEBSITE: https://wisconsindot.gov/Pages/projects/by-region/sw/us51-corridor/northstudy.a…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/12/2028

1 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

No icon

States

Description:

The Wisconsin Department of Transportation (WisDOT) is evaluating reconstruction of US 51/Stoughton Road from WIS 30 in the city of Madison to Interstate 39/90/94 in the town of Burke, a
distance of approximately 5.2 miles. The purpose of the project is to accommodate existing and future travel demand with a focus on safety issues that affect travel on US 51 (Stoughton Road).The need for transportation improvements throughout the US 51 (Stoughton Road) North Study corridor is demonstrated through the following factors:
• Safety, including bicycles and pedestrians
• Travel Demand and Traffic Operations
• Roadway and Geometric Deficiencies

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete