US 59 Relief Route (Future I-369)

PROJECT WEBSITE: https://www.txdot.gov/projects/projects-studies/atlanta/us59-harrison-county.ht…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/20/2024

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The proposed improvements would include:

  • Construction of a new location controlled-access freeway with two 12-foot mainlanes in each direction with inside and outside shoulders and grassy medians
  • One-way frontage roads with two 12-foot travel lanes on either side of the proposed roadway and along I-20
  • On- and off-ramps throughout the length of SL 390
  • Reconstruction of 3 miles of the main lanes along I-20
  • Bridges would be constructed over Eight Mile Creek, Parker Creek, and associated tributaries
  • Improvements to existing cross-streets include:
    • Construction of an underpass at US 80, Buck Sherrod Road, and I-20
    • Construction of a double roundabout at FM 31/Elysian Fields Road

The proposed project is anticipated to require approximately 563 acres of new right of way.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete