US 70 Havelock Bypass
PROJECT WEBSITE: https://www.ncdot.gov/projects/us-70-havelock-bypass/Pages/default.aspx
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/01/2016
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
Bypass on the southwest side of Havelock and U.S. 70 beginning north of the Havelock city limit and extending south approximately 10 miles to north of the Craven-Carteret county line. The Havelock Bypass will be a four-lane, median-divided highway that will provide a high-speed alternative to using U.S. 70 through Havelock, which is hampered by numerous traffic signals at intersecting side streets. The roadway will help improve traffic and freight movement along the U.S. 70 Corridor – a major connection from the Morehead City Port to Raleigh – and assist economic development in eastern North Carolina’s rural areas.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|