USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

US 79

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/01/2029

1 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The Texas Department of Transportation (TxDOT) Austin District is proposing improvements to United States Highway 79 (US 79) between Interstate 35 (I-35) to east of Farm-to-Market Rd 1460 (FM 1460) within the city of Round Rock in Williamson County, Texas. 
Existing Facility
Within the project limits, US 79 consists of four 12-foot main lanes (two in each direction) with 10-foot outside shoulders. Some locations along the corridor have a central turn lane measuring 14 feet. The existing US 79 right-of-way (ROW) varies from 150 to 300 feet wide. 
Proposed Facility
Proposed improvements include widening the existing US 79 roadway to add a third travel lane in each direction and installing a raised median for safety. Improvements to intersections would include potential overpasses at US 79/Mays Street and US 79/FM 1460, and altering the US 79/I-35 Intersection. Driveways and access points would be modified to improve safety and traffic flow. The proposed improvements also include installing shared-use paths on both sides of US 79 to improve pedestrian and bicycle accommodations. The proposed project would require approximately 7.07 acres of new right-of-way.
Figures used in this PCR were made from a combination of provided information on alternative design options.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete