US 79
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/01/2029
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
Texas
Description:
The Texas Department of Transportation (TxDOT) Austin District is proposing improvements to United States Highway 79 (US 79) between Interstate 35 (I-35) to east of Farm-to-Market Rd 1460 (FM 1460) within the city of Round Rock in Williamson County, Texas.
Existing Facility
Within the project limits, US 79 consists of four 12-foot main lanes (two in each direction) with 10-foot outside shoulders. Some locations along the corridor have a central turn lane measuring 14 feet. The existing US 79 right-of-way (ROW) varies from 150 to 300 feet wide.
Proposed Facility
Proposed improvements include widening the existing US 79 roadway to add a third travel lane in each direction and installing a raised median for safety. Improvements to intersections would include potential overpasses at US 79/Mays Street and US 79/FM 1460, and altering the US 79/I-35 Intersection. Driveways and access points would be modified to improve safety and traffic flow. The proposed improvements also include installing shared-use paths on both sides of US 79 to improve pedestrian and bicycle accommodations. The proposed project would require approximately 7.07 acres of new right-of-way.
Figures used in this PCR were made from a combination of provided information on alternative design options.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|