US 82 Widening
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/16/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The United States Highway 82 (US 82) project would extend approximately 16 miles from the Fannin County Line to Loop 286 in western Lamar County. The proposed improvements would widen US 82 from a two-lane undivided highway to a four-lane divided highway with a depressed center median. Improvements to intersecting roads and driveways would be implemented at various locations throughout the project. Intersecting facility improvements would not extend beyond the proposed right-of-way (ROW) boundary. The existing US 82 facility lies within 115 feet minimum, 230 feet maximum width ROW. The proposed project would expand the ROW to 227 feet minimum, 503 feet maximum width. Additionally, the proposed project would require approximately 1.89 acres of proposed permanent easements. The drilled shafts for the bridge columns will be installed to an approximate depth of 30 feet in at least one location.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|