US 90
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/01/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
The following improvements are proposed to improve mobility.
US 90 main lanes
The project would add a third main lane each way between SH 211 and Loop 410, thereby expanding main lanes from four lanes to six lanes between IH 410 and SH 211. This will match the 6 lane section that begins at IH 410 and continues to downtown San Antonio.
US 90 frontage roads
The project would add new, one way frontage roads to both sides of US 90 from Loop 1604 to SH 211. New ROW is required in this area for the frontage roads.
US 90 Ramps
New ramps would be constructed in conjunction with the new frontage roads. Recent projects adjusted ramps in the remainder of the project limits; however additional ramp revisions may be included in the project.
Interchange Improvements
• SH 211 Interchange - A variety of designs will be considered in the process of developing the build alternative here. Innovative intersections will be considered.
• Loop 1604 - Direct connectors would be constructed between US 90 and Loop 1604.
• Montgomery Lane - Expand Montgomery Rd / John Ryan Blvd grade separations, add U-turns
• Hunt Lane – At-grade improvements would be proposed here.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|