Vasquez Boulevard (I-270 to 64th Avenue)
PROJECT WEBSITE: https://www.codot.gov/projects/vasquez-improvements-i270-to-64th
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/12/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
The Vasquez project will improve operations at the intersection of 60th and Vasquez. Improvements include elimination of left turns from Parkway Drive, reduction of outbound movements into the 60th and Vasquez intersection, addition of local access roads, and improvements to 62nd Avenue.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|