USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Walnut Ridge to Missouri State Line (Future I-57)

PROJECT WEBSITE: https://future57.transportationplanroom.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

3 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

No icon

Arkansas

Description:

Project will complete future I-57 from Walnut Ridge, AR into southeast Missouri.  The project alternatives are roughly 42 miles in length. The EIS will evaluate the environmental effects of all reasonable project alternatives and determine the potential impacts to social, economic, natural, and physical environmental resources associated with these alternatives.  The project is needed because there is a gap in the system linkage that diminishes connectivity and mobility of the National Highway System. Additionally, there is a lack of reliable transportation infrastructure to support economic development and a need to enhance resiliency to extreme weather events along the route. Furthermore, Federal legislation designated
this high priority corridor as future Interstate Route 57 (I-57). The project’s purpose is to develop an interstate highway system that addresses the above-described needs while minimizing the negative impacts to the natural and social environment. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete