Washington State Convention Center Expansion

PROJECT WEBSITE: Special Project of the Washington State Convention Center

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/23/2018

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

7/31/18 Rachel Mills-Coyne (copied over from PAPAI): This project proposes to construct a building which will encroach upon the airspace of I-5 (one corner extends over an existing off-ramp).  It will also require the closure of an off-ramp. These and other right-of-way approvals constitute the FHWA nexus for the project.  There is some controversy (primarily from the operators of an adjacent historic theater) and there was an EIS at the state level (SEPA).

The purpose of the project, as currently defined, is to construct an addition to the existing Washington State Convention Center.

(copied from project website): Following the years of study and demand from convention goers who prefer to meet in Seattle, the Washington State Convention Center (WSCC) is proposing to build an additional facility.  The WSCC Addition will be a transformative project that provides a host of economic benefits, including as much as $240 million annually in visitor spending, as many as 3,900 direct and indirect jobs, and some 6,000 jobs during construction. The funding will come primarily from a bond issuance by WSCC supported by the existing tax on hotel rooms.

WSCC has a strong, voluntary commitment to partnering with WMBE businesses. These companies are critical to making the WSCC Addition a success.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete