Washington Union Station Expansion Project
PROJECT WEBSITE: Washington Union Station Expansion Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/12/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
Department of Transportation, Federal Railroad Administration
Description:
The Union Station Redevelopment Corporation (USRC) in coordination with Amtrak is proposing to expand and modernize Washington Union Station, the National Capital Region’s principal intermodal transportation hub. The purpose of the Washington Union Station Expansion Project (the Project) is to support current and future long‐term growth in rail service and operational needs; achieve compliance with the Americans with Disabilities Act (ADA) and emergency egress requirements; facilitate intermodal travel; provide a positive customer experience; enhance integration with the adjacent businesses, neighborhoods, and planned land uses; sustain the Station’s economic viability; and support continued preservation and use of the historic station building. The Project is needed to improve rail capacity, reliability, safety, efficiency, accessibility, and security, for both current and future long‐term railroad operations at this historic station.
FRA encourages and anticipates public participation throughout the development and evaluation of the Project. The FRA website will be updated periodically with project milestones, information about additional public meetings, and other pertinent project information. Comments may be submitted by email to info@wusstationexpansion.com. Thank you for your interest and participation in this important transportation project.
In addition, pertinent information can be found at the project's FRA webpage,
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|