West Lake Corridor
PROJECT WEBSITE: NICTD West Lake Corridor Project Website
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/09/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Other Agencies with Actions or Authorizations:
Indiana
Description:
The West Lake Corridor Project (Project) proposed by the Northern Indiana Commuter Transportation District (NICTD) is located in Lake County, Indiana and Cook County, Illinois. The proposed Project would involve an approximately 9-mile southern branch extension to NICTD's existing South Shore Line (SSL) between Dyer and Hammond, Indiana. Additionally, the Project would operate on approximately 15 miles of existing SSL and Metra Electric District's (MED) line to the Millennium Station in Downtown Chicago. Alternatives being considered include a No Build, Commuter Rail, and several design options for the latter in terms of route alignment, station locations, and vehicle mode. The Project has been proposed to increase transportation options for central and southern Lake County residents traveling to Downtown Chicago, reduce travel time and travel costs, and promote economic development opportunities for Lake County.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|