USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Southeast Gateway Line Project (formerly West Santa Ana Branch Transit Corridor)

PROJECT WEBSITE: Southeast Gateway Line

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/31/2026

2 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

No icon

Department of Defense, US Army Corps of Engineers - Regulatory

Description:

The Los Angeles County Metropolitan Transportation Authority (LACMTA) proposes to construct a light rail transit (LRT) system that would connect several cities and communities in southeast Los Angeles County, California. The Project's initial segment, and Locally Preferred Alternative (LPA) consists of a 14.5 mile LRT segment that would connect several cities between its termini at the Slauson/A Line (blue) connection and Pioneer stations, and would include shifting/realignment of existing freight rail for a distance of approximately 8.7 miles along this alignment. The project includes nine stations plus a tenth station on the "C" Line at I-105, five with parking facilities, and one Maintenance and Storage Facility.   

 

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete

Environmental and Community Outcomes

Categories
Social and Economic Impacts (e.g., environmental justice, displacements)

The project involves the construction and operation of a new 14.5-mile light rail transit line. Based on agency and public input received during the environmental review process, changes to the project were considered and carried forward as part of the project design. For example, a new design option to close 186th Street instead of closing 187th Street was identified during stakeholder coordination after circulation of the Draft EIS/EIR in order to both minimize the number of at-grade crossings along the alignment and take into consideration community input into where permanent road closures were most appropriate. The design option was evaluated in the Final EIS/EIR, and was incorporated into the Locally Preferred Alternative, which has resulted in a safety benefit for the surrounding community. Additionally, in response to comments from property owners and a freight rail operator, the project design was refined to avoid a full acquisition of a property, which avoided impacts to businesses. Furthermore, the location of a traction power substation was changed to avoid a planned bike trail extension, which avoided conflicts with the planned recreational amenity for the community. The project design was also refined as a result of agency comments to change the Artesia Station parking structure access points and signalize the intersection, which will facilitate vehicle circulation and safety.  Another modification was the inclusion of vertical screening elements where aerial structures would be situated adjacent to the rear of residential properties, which was a measure identified to address privacy concerns raised in public comments.