West Virginia International Yeager Airport Airfield, Safety, and Terminal Improvement Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Description:
The West Virginia International Yeager Airport (CRW) Airfield, Safety, and Terminal Improvement Project (Proposed Project), as proposed by the Central West Virginia Regional Airport Authority (Airport Authority), would construct various airfield, safety, and terminal improvements.
To address airport safety in the near term (Phase 1), the Airport Authority proposes to shift and extend Runway 5-23 to the northeast (Runway 23 end) to allow for a Runway Safety Area (RSA) that meets Federal Aviation Administration (FAA) standards on both ends of the runway and to meet existing runway length requirements of 7,000 feet based on the existing operating aircraft fleet and destinations served at CRW. The Airport Authority also proposes to construct a new terminal complex to address terminal area inefficiencies that include an aging and poorly configured terminal facility; relocate taxiways adjacent to the terminal area that are not consistent with FAA design standards; and provide modern amenities that allow for a better passenger experience.
To address long-term capacity needs, Phase 2 of the Proposed Project would include a further shift and extension of Runway 5-23 to 8,000 feet, relocation of the remaining portions of Taxiway A that do not meet FAA design standards, and the development of an additional gate at the terminal facility, which may require the relocation of the existing Airport Traffic Control Tower.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|