USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

West Virginia International Yeager Airport Airfield, Safety, and Terminal Improvement Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Cancelled

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation

SECTOR
Aviation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Description:

The West Virginia International Yeager Airport (CRW) Airfield, Safety, and Terminal Improvement Project (Proposed Project), as proposed by the Central West Virginia Regional Airport Authority (Airport Authority), would construct various airfield, safety, and terminal improvements

To address airport safety in the near term (Phase 1), the Airport Authority proposes to shift and extend Runway 5-23 to the northeast (Runway 23 end) to allow for a Runway Safety Area (RSA) that meets Federal Aviation Administration (FAA) standards on both ends of the runway and to meet existing runway length requirements of 7,000 feet based on the existing operating aircraft fleet and destinations served at CRW. The Airport Authority also proposes to construct a new terminal complex to address terminal area inefficiencies that include an aging and poorly configured terminal facility; relocate taxiways adjacent to the terminal area that are not consistent with FAA design standards; and provide modern amenities that allow for a better passenger experience.

To address long-term capacity needs, Phase 2 of the Proposed Project would include a further shift and extension of Runway 5-23 to 8,000 feet, relocation of the remaining portions of Taxiway A that do not meet FAA design standards, and the development of an additional gate at the terminal facility, which may require the relocation of the existing Airport Traffic Control Tower.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete