Western Rail Yard Infrastructure Project
PROJECT WEBSITE: http://www.westernrailyardinfrastructure.com
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/22/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Railroad Administration
Description:
The Federal Railroad Administration (FRA) is preparing an Environmental Impact Statement (EIS) for the Western Rail Yard (WRY) Infrastructure Project under the National Environmental Policy Act (NEPA), 42 U.S.C. § 4321 et seq. and other applicable laws. WRY Tenant LLC (a Related Company) and the National Railroad Passenger Corporation (Amtrak) are partnering in a joint venture. Together, they are seeking Federal financial assistance through the Railroad Rehabilitation and Improvement Financing (RRIF) Program, which is administered by the Build America Bureau (Bureau). FRA is conducting the environmental analysis to ensure compliance with NEPA and other environmental laws.
WRY Tenant, LLC and Amtrak (Project Sponsors) are seeking financial assistance to fund the construction of a Platform and Tunnel Encasement (the Proposed Action) at the 13-acre WRY site (Block 676, Lot 3) between West 30th and 33rd Street and 11th and 12th Avenues in Manhattan, New York County, NY. The 9.8-acre structural steel and concrete Platform will serve as the roof above Metropolitan Transportation Authority’s (MTA) WRY, which is used and operated by the Long Island Rail Road (LIRR) as a commuter railroad storage yard and maintenance facility. The Tunnel Encasement would be constructed of concrete below street level in WRY, be between 50 ad 65 feet wide and between 27 and 38 feet high. New construction would extend from Eastern Rail Yard at Eleventh Avenue to 30th Street. No permanent operational components—such as tracks, lighting, ventilation, or electrical system—would be constructed within the Tunnel Encasement as part of the proposed action. The Platform would also support the privately funded mixed-use development (Overbuild) approved through New York City zoning for redevelopment of the WRY parcel. This construction also supports MTA’s overall business plan to generate revenue.
Project documents will be made available on the project’s website at www.westernrailyardinfrastructure.com and at Regulations.gov, Docket No. FRA-2020-0039.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|