Westside Purple Line Extension Phase II
PROJECT WEBSITE: Westside Purple Line
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/01/2017
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
Department of Transportation, Federal Transit Administration
Description:
The Purple Line Extension Transit Project is a critically important rail project that will provide a high-capacity, high-speed, dependable alternative for commuters to travel between downtown Los Angeles and Westwood in just 25 minutes. The extension will be built in three sections and will continue from the current station at Wilshire/Western, extending westward for about nine miles along Wilshire Bl. The extension will include seven new stations at Wilshire/La Brea, Wilshire/Fairfax, Wilshire/La Cienega, Wilshire/Rodeo, Century City/Constellation, Westwood/UCLA, and Westwood/VA Hospital.This new Metro Rail extension will offer an alternative transportation option to congested roadways, provide significant environmental benefits and spur economic development throughout the county. Through improved connectivity, riders will be better able to use the entire Metro Rail system, municipal bus lines and other regional transportation services.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|