Atlantic Sunrise
PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 22, 2016PROJECT WEBSITE: http://atlanticsunriseexpansion.com/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/31/2017
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Pipelines
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Description:
Atlantic Sunrise (Docket No. CP15-138-000) would provide an additional 1.7 Bcf/d of natural gas transportation service through: (1) construction of 198.45 miles of pipeline in Pennsylvania and Virginia; (2) construction of natural gas compressor facilities in Pennsylvania and Maryland; (3) construction of two new meter stations and three new regulator stations in Pennsylvania; (4) various modifications at seven compressor stations in Maryland, Virginia, and North Carolina; and (5) modifications at 42 meter stations and 10 valve sites in North Carolina and South Carolina The Atlantic Sunrise amendment (Docket No. CP17-212-000) alters the pipeline route in Pennsylvania by shifting the centerline to the west to address landowner and Federal agency concerns, thereby adding approximately 1.6 miles to the route.
Project Application and Supporting Documents
- Atlantic Sunrise, Project Application, Part 1, FERC Docket No. CP15-138-000 (submitted 03/31/2015). Document located at: http://elibrary.ferc.gov/IDMWS/common/OpenNat.asp?fileID=13820971.
- Atlantic Sunrise, Supporting Documents to Project Application, FERC Docket No. CP15-138-000 (submitted 03/31/2015). Documents located at: http://elibrary.ferc.gov/IDMWS/search/intermediate.asp?link_file=yes&doclist=14318397.
- Transcontinental Gas Pipe Line Company, LLC, Variance Request for Central Penn Line North Alternative 13, FERC Docket No. CP17-212-000 (submitted 04/19/2017). Document located at: https://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14565366.
- Additional Project-related filings and issuances can be found on FERC’s eLibrary website by searching under Docket No. CP15-138.
Federal Agency Actions
- Federal Energy Regulatory Commission, Notice of Schedule for Environmental Review of the Project (issued 03/09/2016). Document located at: https://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14166782.
- Federal Energy Regulatory Commission, Draft Environmental Impact Statement (issued 05/05/2016). Document located at: http://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14240175.
- Federal Energy Regulatory Commission, Revised Notice of Schedule for Environmental Review of the Project (issued 10/20/2016). Document located at: http://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14380180.
- Federal Energy Regulatory Commission, Final Environmental Impact Statement (issued 12/30/2016). Document available at: https://cms.ferc.gov/final-environmental-impact-statement-atlantic-sunrise-project .
- Federal Energy Regulatory Commission, Order Issuing Certificate (issued 02/03/2017). Document located at: https://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=14483853.
- Federal Energy Regulatory Commission, Environmental Assessment (issued 05/18/2017). Document available at: https://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14590770.
- Federal Energy Regulatory Commission, Order Amending Certificate (issued 05/18/2017). Document located at: https://elibrary.ferc.gov/IDMWS/common/opennat.asp?fileID=14591394.
FERC Litigation
- None filed.
State Agency Permitting Timetable for the Atlantic Sunrise Project | ||||
Responsible State Agency | Federal Permit/Review | Intermediate Completion Date | Final Completion Date | Description Field |
Pennsylvania Historical and Museum Commission, Bureau for Historic Preservation | Section 106 NHPA Cultural Resources Review | N/A | 8/4/2017 | Complete |
Maryland Department of the Environment | Section 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge Permit | N/A | 2/22/2017 | Complete. |
Virginia Department of Environmental Quality, Water Division | Section 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge Permit | N/A | 12/16/2016 | Complete. |
Last Updated: 09/05/2017
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|