PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 29, 2022PROJECT WEBSITE: Beacon Wind
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Marine Minerals Administration
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Environmental Protection Agency
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Interior, Fish and Wildlife Service
Description:
Beacon Wind proposes to construct and operate an offshore wind farm to be located approximately 20 statute miles (mi) (17 nautical miles [nm], 32 kilometers [km]) south of Nantucket, Massachusetts, and 60 mi (52 nm, 97 km) east of Montauk, New York. Offshore components of the Project will consist of up to 155 wind turbines and up to two offshore substation facilities for a total of up to 157 foundations.
The Executive Director granted a Bureau of Ocean Energy Management request to extend the NEPA, COP, Section 106, ESA-FWS, ESA-NMFS, EFH, MMPA, Section 10/404, Section 408, OCS air permit and NPDES permit completion dates on March 15, 2024. The Executive Director determination is posted here.
On June 7, 2024, the Beacon Wind Dashboard was updated to pause the FAST-41 permitting timetable requirements through October 31, 2024, allowing the project sponsor time to complete its transition of ownership and begin evaluating potential project design changes and permitting strategies related to the submittal of an updated Construction and Operations Plan (COP).
On October 31, 2024, the Dashboard was updated to extend the pause through October 31, 2025, providing additional time to evaluate and determine the final project design envelope (PDE), obtain feedback from stakeholders and agencies, and make decisions regarding submittal of an updated COP.
On October 1, 2025, the Beacon Wind Dashboard was updated to extend the pause on the FAST-41 permitting timetable requirements through May 31, 2026. This step reflects the changing landscape of the global offshore wind industry, as companies adapt to evolving market conditions and supply chain realities while continuing to advance near-term and long-term opportunities.
On May 8, 2026, Beacon Wind requested a one‑year extension of the existing FAST‑41 permitting schedule pause through May 31, 2027. If the project sponsor elects to submit an updated COP, BOEM will have 60 days from receipt to provide a Coordinated Project Plan (CPP) and publish an updated permitting timetable.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|