Central Louisiana Regional Carbon Storage Hub - Vernon Parish One CCS Site

PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 11, 2023

PROJECT WEBSITE: CapturePoint website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Cancelled

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

CO2 in cloud image

SECTOR
Carbon Capture and Sequestration

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Environmental Protection Agency

LEAD AGENCY
Environmental Protection Agency

View FAST-41 Postings by Agencies

Description:

FAST-41 coverage has been cancelled. EPA granted the State of Louisiana primary enforcement responsibility or "primacy" for implementing a Class VI UIC program on February 5, 2024. Accordingly, Louisiana is now the UIC permitting authority, and there is no longer an EPA federal environmental review or authorization required for this project.

Project Background

The Central Louisiana Regional Carbon Storage Hub – Vernon Parish One Carbon Capture and Sequestration Site Project (project) is a proposed CO2 geologic storage sequestration project located in Vernon Parish, Louisiana near the town of Leesville.  The project will consist of multiple injection and monitoring wells beneath private lands.

The injection capacity is expected to grow from 2.0 million metric tonnes (MMTPA) in 2024 to 5 MMTPA in 2027 and 7 MMTPA in 2029.  The project is anticipated to last for 20 to 25 years and will cumulatively sequester approximately 140 million metric tonnes of CO2 over the life of the project. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete