Dewey Burdock ISR Uranium Project

PERMITTING DASHBOARD PROJECT POSTING DATE: AUGUST 28, 2025

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/29/2026

0 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Nuclear Regulatory Commission

LEAD AGENCY
Nuclear Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Bureau of Land Management

Description:

The Dewey Burdock In-Situ Recovery (ISR) Uranium Project is a proposed uranium production facility located in Fall River and Custer Counties, South Dakota. The project will recover uranium from subsurface sandstone ore bodies through ISR technology, which involves the injection of a lixiviant solution into production wellfields to dissolve uranium minerals in place and pump the uranium-bearing solution to a central processing plant for recovery. The use of ISR technology allows for minimal surface disturbance compared to conventional open-pit or underground uranium mining. The project consists of wellfield areas, a central processing plant, supporting infrastructure and environmental protection systems. The project has been licensed by the NRC (Source Material License SUA-1600) and is progressing toward final state and federal authorizations required to begin commercial production.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete