Energy Gateway South Transmission Project
PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 22, 2016PROJECT WEBSITE: Energy Gateway South Transmission Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/23/2017
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Electricity Transmission
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
Other Agencies with Actions or Authorizations:
Department of the Interior
Description:
The Applicant proposes to construct, operate, and maintain a 500-kilovolt (kV), overhead, single-circuit, alternating-current transmission line beginning near Medicine Bow, Carbon County, Wyoming, at the Aeolus Substation, planned as part of Gateway West, and would extend south and west to Clover Substation (constructed as part of Gateway Central) near Mona, Juab County, Utah, an approximate distance of 425 miles (230 miles on BLM lands). The Project includes two series compensation stations at points between the Aeolus and Clover substations to improve transport capacity and efficiency of the transmission line. Equipment to accomodate the 500kV transmission line would be installed at the Aeolus and Clover substations.
The Project is designed to provide up to 1,500 megawatts (MW) of capacity to meet current and forecasted needs of the Applicant's customers. Additionally, two existing 345kV transmission lines between the Clover and Mona substations, approximately 3 miles apart, would be rebuilt to increase capacity as part of the Project. The lines would be rebuilt in the existing rights-of-way. Part of the Project, the existing Mona to Huntington 345kV transmission line, which passes in a north-south direction to the east of the Clover Substation, would be rerouted through Clover Substation.
Map of project (pages 2-93 and 2-95): https://eplanning.blm.gov/epl-front-office/projects/nepa/53044/73681/80929/007_Ch2_PropAction-Alternatives.pdf
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|