Grants Precision ISR Project
PERMITTING DASHBOARD PROJECT POSTING DATE: MAY 14, 2025PROJECT WEBSITE: Grants Precision ISR
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/26/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Nuclear Regulatory Commission
View FAST-41 Postings by Agencies
Description:
The Grants Precision In-Situ Recovery (Grants ISR) Project proposes to build and operate a uranium extraction and processing facility. This facility will create a new uranium supply from the largest contiguous uranium resource in the United States. The project is entirely on private land in northwestern New Mexico, on approximately 6 square miles of land along the border of Cibola and McKinley counties, approximately 20 miles northeast of Grants New Mexico, near the town of San Mateo.
This project combines In-Situ Recovery (ISR), a widely used method of uranium extraction, with horizontal wells, a method used in oil and gas extraction. ISR uses wellfields to extract uranium from underground ore deposits without the need for open pits or underground mines. The Grants ISR Project would provide over 30 years of uranium supply.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|