Kawich Solar Project

PERMITTING DASHBOARD PROJECT POSTING DATE: JULY 24, 2025

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Planned

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PLANNED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
PENDING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Description:

The Kawich Solar Project includes a 350 MW of PV solar generation and up to 350 MW of battery energy storage on approximately 4,320 acres of federal lands. The Project would be sited entirely on Bureau of Land Management (BLM) land in Indian Springs Valley, in Clark County, Nevada. The Kawich Solar Project Project would interconnect to the existing 230 kV transmission line, between the GridLiance Innovation and Desert View Substations, approximately 2 miles south of the Project.