Kilbourne Graphite Project

PERMITTING DASHBOARD PROJECT POSTING DATE: OCTOBER 10, 2025

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Planned

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PLANNED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
PENDING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

View FAST-41 Postings by Agencies

Description:

The Kilbourne Graphite Project includes an open-pit mine, associated waste rock and tailings management facilities, and an on-site processing plant.  This would include a fully integrated natural flake graphite mine and processing facility producing up to 40,000 tonnes per year of graphite concentrate along with purified and micronized products for industrial, energy, and defense applications.  Total project disturbance is expected to be approximately 600-800 acres.  The project is located in the northern Adirondack Lowlands in Fowler, St. Lawrence County, New York.

Permitting Timetable

Planned Environmental Review and Permitting processes