USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

La Jara Mesa Project

PERMITTING DASHBOARD PROJECT POSTING DATE: MAY 30, 2025

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/31/2028

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Agriculture

LEAD AGENCY
Department of Agriculture, US Forest Service

View FAST-41 Postings by Agencies

Description:

The La Jara Mesa Project proposes development of underground uranium mining and surface support facilities, planned over a 20-year period, on U.S. Forest Service land within the Mt. Taylor Ranger District of the Cibola National Forest, approximately 10 miles northeast of Grants, New Mexico. The project area encompasses about 16.5 acres in Cibola County. 

The project involves the extraction of uranium ore for offsite processing and will be carried out in two phases: underground development and mine production. Surface infrastructure will include two adit portals, waste rock and ore storage areas, a vertical escape shaft, stormwater ponds, ventilation systems, and temporary facilities for workers. Additionally, new water and electrical lines are proposed to follow existing roads to the site.

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete