Larrea Solar Project

PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 13, 2025

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/12/2028

0 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Larrea Solar project includes the construction, operation and maintenance, and decommissioning of an up to 205 MWAC photovoltaic solar facility and an up to 300 MW Battery Energy Storage System (“BESS”). The Project site would be on up to approximately 1,233 acres of federal land managed by BLM located in the Pahrump Valley in Clark County, Nevada and is located approximately 38 miles west of Las Vegas and southeast of the Town of Pahrump. The interconnect is planned at the Trout Canyon Substation at the intersection of SR-160 and Tecopa Road approximately 4.9 miles north of the site. All Project facilities would be located on lands administered by the BLM.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete