Mountain Valley and Equitrans Expansion Project

PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 22, 2016

PROJECT WEBSITE: https://www.mountainvalleypipeline.info/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/23/2023

21 out of 21

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, National Park Service

Department of the Interior

Department of the Interior, Bureau of Land Management

Department of Agriculture

Department of Agriculture, US Forest Service

Description:

On August 18, 2022, Mountain Valley Pipeline, LLC submitted a FAST-41 Initiation Notice for the outstanding federal environmental reviews and authorizations for the project following associated court decisions. A determination of FAST-41 coverage was made on September 1, 2022. 

The project was previously in the initial inventory of FAST-41 covered projects designated by the Executive Director of the Federal Permitting Improvement Steering Council in September 2016 before being closed out on the Permitting Dashboard in late 2017.  

As described in the project sponsor’s FAST-41 Initiation Notice, the project includes the construction of approximately 304 miles of natural gas pipeline in West Virginia and Virginia, three new compressor stations in West Virginia, metering stations, taps, and appurtenant facilities. The project would provide up to 2,000,000 dekatherms per day of firm natural gas transportation service from northern West Virginia to southwestern Virginia.

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete