North Anna Power Station, Unit 3
PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 22, 2016PROJECT WEBSITE: http://www.nrc.gov/reactors/new-reactors/col/north-anna.html
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/02/2017
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Conventional Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects

LEAD AGENCY
Nuclear Regulatory Commission, Office of New Reactors
Other Agencies with Actions or Authorizations:

Nuclear Regulatory Commission
Description:
Dominion Virginia Power seeks approval for constructing and operating a new ESBWR reactor unit at the North Anna Power Station site to provide additional electricity for use in the midatlantic service areas. The new unit would be capable of providing an additional 1500 megawatts of baseload electricity. The combined license was issued on June 2, 2017.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|